Sidewalk Preparation Continues


downtown parking sign.

Downtown Construction
Weekly Update - September 5, 2007

MAIN STREET UPDATE

CONSTRUCTION UPDATE

ACCOMPLISHED

  • Curb installation was completed along the east end of Main Street.
  • Paving installation for on-street parking continued along Main Street.
  • Grading work for sidewalks continued.
  • Relocation of the sanitary sewer line has been completed for the new plaza area. Gas line installation will continue.
  • Installation work continued on the foundations for the new streetlights.

OUTLOOK FOR THE NEXT TWO WEEKS:

  • Installation of curbs in the downtown area will be completed.
  • Gas line relocation will be completed for the new plaza area.
  • Installation of light pole foundations will continue.
  • Grading for sidewalks will continue. Installation of the sidewalks may begin within the next two weeks.
  • Installation work will begin on the driveway aprons.

MASON-MONTGOMERY ROAD PROJECT

ACCOMPLISHED THUS FAR:

  • The installation of driveway aprons has begun.
  • Installation of the underground conduit began for the new street lighting.
  • Crews have begun pouring sidewalks along Mason-Montgomery Road.
  • Duke Energy continued the relocation of the overhead electric lines to the new utility poles.

OUTLOOK FOR NEXT TWO WEEKS:

  • Installation work will begin on the foundations for the streetlights.
  • Tie-ins and services for the gas line will be completed.
  • Cincinnati Bell, Time Warner, and Embarq will begin relocating the overhead lines to the new utility poles.
  • Sidewalk and curb removal will begin in front of the firehouse and parking area near the intersection of Mason-Montgomery Road and Main Street.