Downtown Construction
Weekly Update - September 12, 2007
MAIN STREET UPDATE
CONSTRUCTION UPDATE
ACCOMPLISHED
- Installation of sidewalks continued along Main Street, from North West Street to North East Street.
- Transformer pads have been set.
- Grading work for sidewalks continued.
- Installation of conduit has begun for street tree power receptacles.
- Installation work continued on the foundations for the new street lights.
OUTLOOK FOR THE NEXT TWO WEEKS:
- Grading and curb installation work will begin on the plaza area.
- Footer installation work will begin on the three stone walls for the plaza.
- Installation of light pole foundations will continue.
- Grading for sidewalks will continue. Installation of the sidewalks continues on Main Street, between North East Street and Mason-Montgomery Road.
- Installation work continues on the driveway aprons.
MASON-MONTGOMERY ROAD PROJECT
ACCOMPLISHED THUS FAR:
- The installation of sidewalks will continue.
- Installation of the underground conduit continues for the new street lighting foundations.
- Restoration work has begun. Crews will begin seeding, mulching, and laying topsoil for the yards affected by the construction.
- Grading work has been completed on the bike path along Mason-Montgomery Road.
- Duke Energy completed relocating the overhead electric lines to the new utility poles.
OUTLOOK FOR NEXT TWO WEEKS:
- Installation work will continue on the foundations for the streetlights.
- Work will continue on tie-ins and services for the gas line.
- Cincinnati Bell, Time Warner, and Embarq will relocate their overhead lines to the new utility poles.
- Sidewalks have been removed in front of the firehouse and parking area near the intersection of Mason-Montgomery Road and Main Street. Workers will begin installing curbs.
OTHER NOTES OF INTEREST:
- Crews are awaiting Duke Energy’s completion of the gas line tie-ins. Once completed, work can begin on opening up the northbound lanes of traffic along Mason-Montgomery Road.