Downtown Construction
Weekly Update - September 19, 2007

MAIN STREET UPDATE

CONSTRUCTION UPDATE

ACCOMPLISHED

  • Sidewalk installation continued along Main Street.
  • Installation work began on the foundations for the plaza walls.
  • Driveway aprons installation continued.
  • The traffic signal on the corner of North West Street and Main Street was removed.
  • Paving work has continued in areas along Main Street.

OUTLOOK FOR THE NEXT TWO WEEKS:

  • Grading and curb installation work will continue on the plaza area.
  • Concrete base installation work for pavers will continue at the west corner of Mason-Montgomery Road and Main Street.
  • Construction work on the planting walls of the plaza area will begin.
  • Installation of the sidewalks will continue on Main Street.
  • Installation work will continue on the driveway aprons.

MASON-MONTGOMERY ROAD PROJECT

ACCOMPLISHED THUS FAR:

  • Installation of curbs and driveway aprons was completed in front of the firehouse.
  • Installation of the underground conduit continued for the new street lighting foundations.
  • Restoration work continued. Crews are seeding, mulching, and laying topsoil for the yards affected by the construction.
  • Installation of asphalt continued. Crews completed installing the base course in front of the firehouse. Crews also installed the final course of asphalt for the bike path.
  • Cincinnati Bell began relocating fiber optic lines.

OUTLOOK FOR NEXT TWO WEEKS:

  • Mason-Montgomery Road will re-open to northbound traffic between Church and North Streets, likely today or tomorrow.
  • Paving work began along the intersection of North Street and Mason-Montgomery Road.
  • Storm sewer installation work continued across North Street.
  • Once Cincinnati Bell completes fiber optic relocation, Time Warner will start the cable relocation.