Curb Work Completed on Reading Road and North West Street


plaza wall foundation

Downtown Construction
Weekly Update - October 3, 2007

MAIN STREET UPDATE

CONSTRUCTION UPDATE

ACCOMPLISHED

  • Crews installed sidewalks and are pouring driveway aprons in various locations.
  • Wall installation began for the plaza area and parking lot adjacent to 111 Reading Road.
  • Workers continued to install light pole foundations.
  • Conduit has been installed in the plaza area for streetlights and the irrigation system.
  • Curbs were poured on Reading Road and North West Street.
  • Mud slab was poured for the paver area in front of Miami Valley Floral.
  • Duke Energy began pulling wire for underground electric.
  • Time Warner began pulling wire for underground cable.

OUTLOOK FOR THE NEXT TWO WEEKS:

  • Sidewalk and driveway apron installation will continue in various locations.
  • Wall installation will continue in the plaza area and for the parking lot area adjacent to 111 Reading Road.
  • Light pole foundation installation will continue in the plaza area.
  • Conduit installation will continue in the plaza area for streetlights and the irrigation system.
  • Mud slab will be poured for the paver area along Reading Road, as well as at the northwest and southwest corners of Main Street and Mason-Montgomery Road.
  • Electrical services will begin to be transferred from overhead to underground for some individual buildings.

MASON-MONTGOMERY ROAD PROJECT

ACCOMPLISHED THUS FAR:

  • Grading and curb pouring was completed on West North Street.
  • Grading work was finished for the remaining portion of the bike path on Mason-Montgomery Road.
  • Sidewalks, driveway aprons, and curb ramps were poured in several locations.
  • Restoration work continued. Crews are continuing to seed disturbed areas.
  • Time Warner continued cable line installation.

OUTLOOK FOR NEXT TWO WEEKS:

  • Paving work will occur on West North Street. Once complete, crews will re-open the street for westward one-way traffic.
  • Paving work on the bike path will be completed.
  • Pouring of driveways, sidewalks, and aprons will be completed.
  • The restoration and seeding of disturbed areas will continue.
  • Streetlight foundation installation will begin.