Downtown Construction
Weekly Update - October 10, 2007
MAIN STREET UPDATE
CONSTRUCTION UPDATE
ACCOMPLISHED
- Crews have installed sidewalks and are pouring driveway aprons in various locations.
- Wall installation continued in the plaza area and the parking lot adjacent to 111 Reading Road.
- Workers installed light pole foundations in the plaza area.
- Mud slab was poured for the paver area in front of Fifth Third Bank.
- Duke Energy began pulling wire for underground electric.
- Time Warner continues to pull wire for underground cable.
- The first underground electric hook up was completed for 125 West Main Street.
- Workers have started installation of the pavers on the north side of Main Street.
OUTLOOK FOR THE NEXT TWO WEEKS:
- Sidewalk and driveway apron installation will continue in various locations.
- Wall installation will continue in the plaza area and for the parking lot area adjacent to 111 Reading Road.
- Conduit installation will continue in the plaza area for street lights and the irrigation system.
- Electrical services will continue to be transferred from overhead to underground for some individual buildings.
MASON-MONTGOMERY ROAD PROJECT
ACCOMPLISHED THUS FAR:
- Conduits for the streetlights will continue to be installed.
- Sidewalks, driveway aprons, and curb ramps were poured in several locations.
- Restoration work continued. Crews are continuing to seed disturbed areas.
- Time Warner continued cable line installation.
OUTLOOK FOR NEXT TWO WEEKS:
- Paving work will occur on West North Street. Once complete, crews will re-open the street for westward one-way traffic.
- Paving work on the bike path will be completed.
- Pouring of driveways, sidewalks, and aprons will be completed.
- The restoration and seeding of disturbed areas will continue.
- Street light foundation installation will begin.
- Time Warner should finish their cable relocation. Once complete, Embarq will begin relocating their phone lines to the new poles.