Downtown Construction
Weekly Update - October 31, 2007
MAIN STREET UPDATE
CONSTRUCTION UPDATE
ACCOMPLISHED
- Crews have continued to install the stone fascia to the walls in the plaza area.
- Duke Energy continues work to prepare for underground service.
- Workers completed the installation of the paver strips along portions of Main Street.
- Conduit installation was completed in the plaza area for streetlights and the irrigation system.
- Waterline service installation was completed for the plaza area.
- Workers are digging out planting areas for the installation of trees and topsoil.
OUTLOOK FOR THE NEXT TWO WEEKS:
- Masonry wall installation will begin in front of the parking lot for Muennich’s Garage and the Barber Shop.
- Crews will pour the new apron for the parking lot as well.
- Street tree installation will begin in the planting areas.
- Workers will continue installing the stone fascia to the walls in the plaza.
- Pavers will be installed in the strips along the sidewalk areas along portions of Main Street.
- Trench, drains, and concrete benches will be installed in the plaza area.
- Electrical services will continue to be transferred from overhead to underground for individual buildings.
- Milling of the asphalt in the roadway is scheduled to begin November 6.
NOTES OF INTEREST:
- Inclement weather continued to cause some delays for crews in certain areas. Mainline was unable to work on Oct. 25 due to poor weather conditions.
MASON-MONTGOMERY ROAD PROJECT
ACCOMPLISHED THUS FAR:
- Conduits for the streetlights will continue to be installed.
- Restoration and seeding work for disturbed areas continued.
- Time Warner Cable completed cable line installation and relocation of fiber optic lines. Embarq is now the last utility on the old poles.
OUTLOOK FOR NEXT TWO WEEKS:
- The restoration and seeding of disturbed areas will continue.
- Embarq will work on the relocation of their services to the new poles. Once they complete their relocation, the old poles can then be removed.