Milling of Roadways Has Begun


paver work continues

Downtown Construction
Weekly Update - November 7, 2007

MAIN STREET UPDATE

CONSTRUCTION UPDATE

ACCOMPLISHED

  • Stone fascia installation continues on the walls in the plaza area.
  • Duke Energy continues preparation work for underground service installation.
  • Installation of the paver strips was completed along portions of Main Street.
  • Installation of trench drains and piping was completed in the plaza area.
  • Crews have poured footers and are working on the walls in front of Muennich’s Garage and the Barber Shop.
  • Installation of pavers has begun at Mason-Montgomery Road at Buskin’s Bakery.
  • Milling of the roadways has begun in preparation for intermediate coarse of asphalt.

OUTLOOK FOR THE NEXT TWO WEEKS:

  • Milling of the roadway will be completed. Crews will then begin paving the intermediate coarse of asphalt.
  • Street tree installation will begin in the planting areas.
  • Installation of the stone fascia will continue on the walls in the plaza, as well as the wall next to the new parking lot.
  • Sidewalk installation in the plaza area will begin.
  • Paver installation will continue at Mason-Montgomery Road and Main Street.
  • Electrical services will continue to be transferred from overhead to underground for individual buildings.
  • Driveway restoration for pavement disturbed by construction will begin.

MASON-MONTGOMERY ROAD PROJECT

ACCOMPLISHED THUS FAR:

  • Restoration and seeding work for disturbed areas continued.
  • Embarq is working on relocating their overhead lines to the new poles.
  • Duke Energy began removing some of the poles where services have been removed.

OUTLOOK FOR NEXT TWO WEEKS:

  • The restoration and seeding of disturbed areas will continue.
  • Embarq will continue relocation of their services to the new poles. Once they complete the relocation, the old poles will be removed.
  • Workers will continue milling and paving the roadway.