Weekly Update - November 14, 2007
MAIN STREET UPDATE
CONSTRUCTION UPDATE
ACCOMPLISHED
- Installation of the fascia stone continued on the walls in the plaza area.
- Installation of the pavers continued on the corner of Main Street and Mason-Montgomery Road.
- Sidewalk installation work has begun in the plaza area.
- Pavement restoration work was completed for some curb cuts along Main Street.
- Milling of the pavement continued and the intermediate course of asphalt is being placed.
- Iron benches have been placed downtown in front of several stores.
- Embarq has begun tying in conduits for underground service installation.
OUTLOOK FOR THE NEXT TWO WEEKS:
- Crews will finish paving the intermediate course of asphalt. Upon completion (and weather permitting), the workers can begin temporary roadway striping.
- Crews will begin pouring cement in the plaza area.
- Street tree installation will begin in the planting areas.
- Driveway aprons will be poured for Muennich’s Garage and Gary’s Barber Shop.
- Paver installation will continue at Mason-Montgomery Road and Main Street.
- Sidewalks will be poured along Main Street.
MASON-MONTGOMERY ROAD PROJECT
ACCOMPLISHED THUS FAR:
- Roadway milling has been completed.
- Crews replaced a section of the driveway apron in front of the fire station.
- Installation work has begun on the retaining wall.
- Duke Energy removed their utility poles from the roadway.
OUTLOOK FOR NEXT TWO WEEKS:
- Retaining wall installation will be completed.
- Paving of the intermediate course of asphalt will be completed. Upon completion, crews will begin temporary striping of the roadway and will prepare to re-open to two-way traffic.
- Embarq will complete their relocation work and remove the old utility poles.