Downtown Businesses Prepare for Christmas in Mason this Saturday, December 7


paver work continues

Downtown Construction
Weekly Update - December 5, 2007

MAIN STREET UPDATE

CONSTRUCTION UPDATE

ACCOMPLISHED

  • Installation of the fascia stone continued on the walls in front of the parking areas.
  • Workers continued the installation of the street trees and ground coverings along Main Street.
  • Paver installation continued in the plaza area.
  • Crews continue to work on the irrigation system for the plaza area.
  • Embarq continues tying in conduits for underground service installation.
  • Sidewalk in and near the plaza area was installed.
  • Duke Energy transferred overhead services to underground west of the plaza and has begun removal of the overhead electrical lines.

OUTLOOK FOR THE NEXT TWO WEEKS:

  • Crews will continue to install pavers in the plaza area.
  • Sidewalk will be poured in front of the Embarq building on Forest Avenue.
  • Installation of the fascia stone will be completed on the walls in the plaza area.
  • Embarq and Time Warner will continue to work on underground lines.

MASON-MONTGOMERY ROAD PROJECT

ACCOMPLISHED THUS FAR:

  • Installation work continues on the streetlight foundations.
  • A catch basin was installed at North Street.
  • Restoration work of disturbed areas with topsoil and seeding continued.

OUTLOOK FOR NEXT TWO WEEKS:

  • Streetlight foundation work will be completed.
  • Embarq is scheduled to complete their relocation work this week and then old poles will be removed the following week, weather dependant.