Downtown Construction
Weekly Update - December 12, 2007
MAIN STREET UPDATE
CONSTRUCTION UPDATE
ACCOMPLISHED
- Installation of the fascia stone continued on the walls in front of the parking areas of the plaza. Work is approximately 85% complete.
- Paver installation continued in the plaza area.
- Embarq has begun installation of underground cables.
- Duke Energy has been replacing poles and upgrading power lines on South West Street.
OUTLOOK FOR THE NEXT TWO WEEKS:
- Crews will continue to install pavers in the plaza area.
- Sidewalk will be poured in front of the Embarq building on Forest Avenue.
- Installation of the fascia stone will be completed on the walls in the plaza area.
- Embarq and Time Warner will continue to work on underground lines.
MASON-MONTGOMERY ROAD PROJECT
ACCOMPLISHED THUS FAR:
- Installation work of streetlight foundations has been completed.
- Restoration work of disturbed areas with topsoil and seeding continued.
- Crews poured foundation for the power cabinet for the street lights.
OUTLOOK FOR NEXT TWO WEEKS:
- Embarq has removed all but three poles. They have contacted Duke Energy to assist with removing the remaining oversized poles.
- Sections of sidewalk where old utility poles were removed will be installed, weather dependent.