Fascia Stone Work Along Plaza Walls is Nearly Completed


paver work continues

Downtown Construction
Weekly Update - December 12, 2007

MAIN STREET UPDATE

CONSTRUCTION UPDATE

ACCOMPLISHED

  • Installation of the fascia stone continued on the walls in front of the parking areas of the plaza. Work is approximately 85% complete.
  • Paver installation continued in the plaza area.
  • Embarq has begun installation of underground cables.
  • Duke Energy has been replacing poles and upgrading power lines on South West Street.

OUTLOOK FOR THE NEXT TWO WEEKS:

  • Crews will continue to install pavers in the plaza area.
  • Sidewalk will be poured in front of the Embarq building on Forest Avenue.
  • Installation of the fascia stone will be completed on the walls in the plaza area.
  • Embarq and Time Warner will continue to work on underground lines.

MASON-MONTGOMERY ROAD PROJECT

ACCOMPLISHED THUS FAR:

  • Installation work of streetlight foundations has been completed.
  • Restoration work of disturbed areas with topsoil and seeding continued.
  • Crews poured foundation for the power cabinet for the street lights.

OUTLOOK FOR NEXT TWO WEEKS:

  • Embarq has removed all but three poles. They have contacted Duke Energy to assist with removing the remaining oversized poles.
  • Sections of sidewalk where old utility poles were removed will be installed, weather dependent.