Roadway Grading Begins


downtown parking sign.

Downtown Construction
Weekly Update - July 25, 2007

MAIN STREET UPDATE

CONSTRUCTION UPDATE

ACCOMPLISHED

  • Underground conduit and utility pull box installation has been completed on the south side of Main Street from Reading Road to Mason-Montgomery Road.
  • Workers have installed a trench drain in front of the floral shop.
  • Grading for roadway realignment has started.
  • Storm sewer installation has been completed except for one section near the plaza area.

OUTLOOK FOR THE NEXT TWO WEEKS:

  • Duke Energy will be setting the utility poles.
  • Work will continue on the conduit and utility pull box installation on the north side of Main Street.
  • Workers will begin excavating for the roadway and curbs.
OTHER ISSUES:

  • There is a duathlon occurring on Sunday. The bike portion of the event will start at Mason Municipal Center and travel north on Mason-Montgomery Road. Police will be coordinating detours around the closed section of Mason-Montgomery Road.

MASON-MONTGOMERY ROAD PROJECT

ACCOMPLISHED THUS FAR:

  • Continued storm sewer work.
  • Hydrants have been relocated and the water line work is now complete.
  • Began excavation for roadway widening and East North Street realignment.

OUTLOOK FOR NEXT TWO WEEKS:

  • Due to the widening of the road, Duke Energy will begin installing new poles.
  • Gas line relocation will begin.
  • Workers will continue the excavation for the roadway and curbs.