Asphalt Placed on New Intersection


downtown parking sign.

Downtown Construction
Weekly Update - August 29, 2007

MAIN STREET UPDATE

CONSTRUCTION UPDATE

ACCOMPLISHED

  • Curbs were installed along West Main Street near Forest Avenue.
  • Relocation of the sanitary sewer and gas line began for the new plaza area.
  • The base course of asphalt was installed at the new intersection near the old Speedway lot.
  • The underground conduit installation from the pull boxes to all of the individual buildings was completed.
  • Installation began on the foundations for the new streetlights.
  • Duke Energy began setting the poles to allow for the transition of utilities from overhead to underground.

OUTLOOK FOR THE NEXT TWO WEEKS:

  • Installation of the curbing and base asphalt in the downtown area will be completed.
  • Sanitary sewer and gas line relocation will be completed.
  • Preparation work will begin on the grade for sidewalks and pavers.
  • Installation of the storm sewers will be completed.
  • Duke Energy will finish setting the new poles.
OTHER NOTES:

  • Due to the Labor Day holiday, the contractor will be off Saturday and Monday.
  • Since school started last Wednesday, the city has been monitoring morning and afternoon traffic to maintain flow.

MASON-MONTGOMERY ROAD PROJECT

ACCOMPLISHED THUS FAR:

  • The gas main was installed. Crews are awaiting an air test prior to tying it in.
  • The base course of asphalt was installed on the east side of Mason-Montgomery Road.
  • Excavation and grading work continued on the west side of Mason-Montgomery Road.
  • Duke Energy has started the relocation of the overhead electric lines to the new utility poles.

OUTLOOK FOR NEXT TWO WEEKS:

  • Tie-ins and services for the gas line will be completed.
  • Installation of the conduit will continue for the new street lighting.
  • The installation of sidewalks will begin.
  • Cincinnati Bell, Time Warner, and Embarq will relocate their overhead lines to the new utility poles.